|
Home
> Articles
By Issue > Building
Envelope & Exteriors > Article Jan. 2002
Building Commissioning:
One Effective Solution To The Building Automation Puzzle
By
E. Thomas Lillie
Lillie & Co.
While the concept of building
commissioning is no longer as alien as it once was,
the process itselfand the resultstill leave
many fms with more questions than answers. Building
commissioning is fairly straightforward: to assure that
the design and installation of a building's equipment
and systems actually satisfy the owner's intent and
to facilitate the turnover of the equipment and systems
to the owner so that operations, preventive maintenance
and troubleshooting programs can be established.
Commissioning became a legitimate
management tool in the 1980s when computerization, technological
advances, and how these systems interact dynamically
with one another made it impossible for fms to verify
if what they had was what they ordered. Too many facilities
did not perform up to expectations.
Over the last two decades, the
service has gained more recognition and credibility
as owners and fms recognize an even greater need for
a third-party to ensure all their expectations are fulfilled.
Assuming that fms understand
the concept of commissioning, they must ask and answer
the following questions before finalizing their commissioning
strategies:
- How do they assure the right
process for their facilities?
- How do they find the right
commissioning agents (CAs)?
- Can the general or mechanical
contractor perform both contracting and commissioning
functions?
- Should all new buildings
be commissioned, or is it unnecessary in some cases?
- What should fms ask for and
what should they expect?
- When should a CA join the
building team, and to whom should he report?
Knowing the answers to theseand
otherconcerns will help make the commissioning
project run smoother and more efficiently.
Asking The Right Questions
Fms need to be sure they
are getting the full benefit of the commissioning process
and the best result for their buildings. Following are
some key questions to help make these determinations.
1. Should all buildings
be commissioned? Do some benefit more than others?
Since the systems that are commissioned are typically
the mechanical, electrical, and life safety systems,
the facilities that benefit most from commissioning
are those where these systems are most complex. This
would include most medical facilities, laboratories,
data centers, and other buildings with critical, integrated
systems.
Schools and colleges are prime
candidates for commissioning due to the nature of the
occupants. Schools typically have the worst environments
of any facilities. Statistics show that teachers suffer
from more illnesses than any other profession.
Venues with special operating
requirements, and those that hold large numbers of people
at any given time, such as high-rise residential buildings,
prisons, hotels, and indoor stadiums, should be commissioned
as well.
Fms of buildings that are owner-occupied,
operated, and maintained would be wise to have them
commissioned. In addition to life safety issues, energy
efficiency, productivity, and self insurance give the
owner a vested interest in the building's efficient
operation.
Recommissioning and/or commissioning
an existing facility can be very beneficial for buildings
that aren't performing as promisedor buildings
whose purpose may have changed over time. Recommissioning
involves performance and diagnostic testing of most
major systems and documented results and recommendations
on how to correct any deficiencies.
2. What systems should be
commissioned? All major components and equipment
comprising the mechanical, electrical, and life safety
systems should be commissioned. In most cases the majority
of the verification involves mechanical systems.
3. Who should provide the
building commissioning services? Must it be a third
party CA, or can the general or mechanical contractor
or the engineer provide this service? The CA must be
an advocate of the owner. If the CA's firm has other
project responsibilities or is not directly responsible
to the owner, a conflict of interest exists. A general
or mechanical contractor verifying building systems
can be like the fox guarding the henhouse. The CA should
be an objective, independent third party.
In addition, the persons conducting
the commissioning service should be professional engineers.
They should have in-depth experience as a designers
of MEP (mechanical, electrical, and plumbing) systems,
as well as field construction and construction management
experience. According to the Building Commissioning
Association (BCA), these individuals should have recent
hands-on field experience regarding:
- Building systems commissioning,
- The physical principles of
building systems performance and interaction,
- Building systems start up,
balancing, testing, and troubleshooting,
- Operations and maintenance
procedures, and
- The building design and construction
process.
4. When should the CA be
brought on board? Ideally, the CA should be part
of the design team at conception. Commissioning transcends
all stages of the development of a new project, including
planning, design, construction, equipment check out
and balancing, owner occupancy, and training of personnel.
Though CAs don't function as
designers, they do assist the fm in analyzing the proposed
designs for optimal operation. The CA's responsibility
includes determining constructability, system efficiency,
and maintainability; identifying critical operating
requirements; and coordinating the mechanical and electrical
trades. As the design is developed, the CA provides
a list of systems to be commissioned, developing testing
and verification parameters, and reviewing all pertinent
construction documents.
5. How much should I expect
commissioning to add to the cost of my project?
On a recent cost comparison of projects which included
the commissioning of new building mechanical and electrical
systems, the commissioning cost typically ran 2.5% of
the total mechanical cost and 1.5% of the total electrical
cost. Another guideline is 2% to 5% of the total cost
of mechanical, electrical, plumbing, and life safety
systems. Classrooms and office buildings typically fall
in the lower range, lab/classrooms and correctional
facilities in the mid-range, and hospitals and hi-tech
laboratories close to the 5% figure.
Some contractors insist on adding
field labor cost due to commissioning. This suggests
that contractors don't test their installed systems.
Most specifications require functional testing so additional
field labor should not be needed.
Consider the importance of a
building that meets expectations. Systems that do not
work translate into time consuming, costly corrective
measures and possible litigation or acceptance of systems
that may never work as planned.
Getting The Right Person
When hiring a CA, the following
criteria should be considered:
Level of Experience. Ask to see a list of the
firm's commissioning projects for the past five years.
Again, commissioning should not be an add-on service
of the firm selected. It should be the primary business.
Organizational Involvement.
Ask to what professional commissioning organizations
the firm belongs. The leading commissioning firms are
members of the Building Commissioning Association (BCA).
Previous Commissioning Plan.
Ask to review a copy of a commissioning planincluding
the final reportfrom a previous project. This
will help fms know what to expect regarding the process
and documentation.
References. Ask for
and contact references of fms with buildings similar
to the one being built.
It is also advisable to interview
construction management firms, general contractors,
and the primary subcontractors that will bid on constructing
the facility regarding their experience with the commissioning
process. Ask each if they have been through a commissioning
process. It is best if the construction manager has
been through the process, good if the general contractor
has, and beneficial if the mechanical and/or electrical
subs are familiar with the experience.
Working Together
Commissioning is not an
independent function. Rather, it is intertwined with
the work of the construction manager and the primary
contractors. All of these parties participate in the
process by way of field testing, as well as the documentation
they provide. Many project managers must rethink the
way they manage a commissioned project because of the
documentation and verification that are required. Needless
to say, if they have been through the process before,
the project should go more smoothly.
Ask the general contractors
who are bidding if they have mechanical and/or electrical
engineers on staff. Those that do will have a background
and a resource that will be extremely helpful in understanding,
supporting, and participating in the process.
Expectations
Once a CA has been selected,
what should the fm expect? The BCA divides commissioning
services into two categories: Essential Attributes and
Variable Elements. Essential Attributes are so fundamental
to effective building commissioning that all members
agree in writing to adhere to them whenever they serve
as a project's CA. Here are some examples of what might
be put into writing before a project is started:
- The CA is in charge of the
commissioning process and makes the final recommendations
to the owner regarding functional performance of the
commissioned building system.
- The commissioning purpose
and scope are clearly defined in the CA contract.
- The commissioning roles and
scope for all members of the design and construction
teams should be clearly defined in each and every
contract, general conditions of the specifications,
each division of the specifications covering work
to be commissioned, and the specifications for each
system and component for which the supplier's support
is required.
- Each project is commissioned
in accordance with a written commissioning plan that
is updated as the project progresses.
- On new building commissioning
projects, the CA reviews systems installation for
commissioning related issues throughout the construction
period
- All commissioning activities
and findings are documented as they occur. These reports
are distributed as they're generated and included
in the final report.
- The functional testing program
objectively verifies that the building systems perform
interactively in accordance with the project documents.
Written, repeatable test procedures prepared specifically
for each project are used to test components and systems
in all modes of operating conditions specified for
testing. These tests are documented to describe the
individual systematic test procedures, the expected
systems response or acceptance criteria for each procedure,
the actual response or findings, and any pertinent
discussion.
- The commissioning authority
provides constructive input for the resolution of
system deficiencies.
- Every commissioning project
is documented with a report that includes:
Labeled as valuable, but not
essential, the CA recommends the building commissioning
scope include the following:
- Prior to design the CA would
assist the fm in evaluating such issues as energy
conservation, indoor environment, staff training,
and operation and maintenance.
- Review all phases of design
and construction documents for compliance with design
criteria, commissioning requirements, bidding issues,
construction coordination and installation concerns,
performance aspects, and facilitation of O&M,
including training and documentation.
- Review equipment submittals
for compliance with commissioning issues.
- Verify or manage the scheduling
and procedures used for system start-up.
- Verify that training for
the operating staff is conducted in accordance with
project documents.
- Verify that O&M manuals
comply with the contract documents.
- Prior to expiration of the
construction contract warranty, assist the owner in
assessing systems performance and addressing related
issues.
Fms might also consider assigning
the testing and balancing function to the CA.
These guidelines should go a
long way towards seeing that best practices are utilized
for commissioning a facility.
On The Books
Other organizations have
commissioning guidelines as well, and some services
that fall under the purview of the CA are required by
law.
The American Society of Heating,
Refrigeration and Air Conditioning Engineers (ASHRAE)
Technical Committee 9.9, Building Commissioning, is
concerned with methods of developing and executing the
commissioning process as required to provide HVAC and
related systems which conform with design intent and
project requirements. ASHRAE offers numerous training
workshops and seminars on building commissioning and
recommissioning.
The National Institute of Building
Sciences, the Florida Design Initiative, the Northwest
Energy Efficiency Alliance, and Portland Energy Conservation,
Inc. also offer building commissioning information and
research services.
The National Fire Protection
Association requires annual testing of life safety systems
and provides the National Electric Code (NEC)a
document which most municipalities and governing bodies
require to be met in order to acquire a construction
permit. The NEC defines commissioning tasks as they
relate to electrical systems. The Institute of Electrical
& Electronics Engineers, the Occupational Safety
& Health Administration, and the American National
Standards Institute all promote standards for commissioning
electrical equipment.
In some states, backflow preventors
are required by law to be tested annually. In certain
areas of the country, primarily in the northwest, some
cities require municipal and/or public projects to be
commissioned. The Department of Energy's Rebuild America
Program, the Federal Energy Management Program, and
the General Services Administration each have commissioning
booklets.
As commissioning becomes more
systematic and gains wider acceptance, its role in the
design/construct industry will expand.
An Ongoing Process
Continuous commissioningestablishing
testing procedures that continue throughout the life
of a buildingis a trend that is taking hold, particularly
in buildings such as laboratories and hospitals that
rely on extremely complex, integrated components and
systems. Because of the CA's familiarity with the building
design and operation, the agent is in the best position
to establish these procedures.
The CA implements a customized
Computer Maintenance Management System (CMMS) that allows
in-house operations and maintenance personnel to monitor
critical systems. CMMS have recently become more affordable
and should be seriously considered for facilitating
preventive maintenance and allowing for optimum performance.
Along with positive trends,
a few negatives always seem to emerge as well. More
contracting, design engineering and testing, and balance
firms are offering building commissioning as a sideline.
When mechanical, electrical,
and/or life safety systems fail, the fm's job can become
a nightmare. Often, the systems fail because they have
never fully performed to expectations. Some problems
become obvious at building startup. Others surface when
the facility is at peak capacity.
In terms of cost, time, efficiency,
and performance, a building that has been commissioned
can make a tremendous difference in the workday of fms.
Toward that end, fms owe it to themselves to understand
the process and the benefits of building commissioning
in order to present the best case for their next facility.
E. Thomas Lillie, P.E.
Lillie is a principal with St. Louis, MO-based Lillie
& Co. For more information, visit www.lillienco.com.
|