|
Home
> Articles
By Issue > Showcase
> Article June
2004
SHOWCASE:
USDA
Choice
The U.S. Department of Agriculture's
(USDA) South Building is undergoing a massive renewal.
By John Parkinson
The USDA's South Building once
had an unofficial honor bestowed upon it. Although its
initial purpose was to house both laboratories and offices,
the building was considered the largest office building
in the world after it was fully constructed in 1936.
Unfortunately, the building
only held this distinction for a few years, until construction
began on the nearby Pentagon in the early 1940s.
While it may have lost its
number one status, this facility that is part of the
USDA's headquarters complex remains a structural feat.
This mammoth building is over two million square feet
and encompasses two city blocks in downtown Washington,
DC. There are six floors, an attic located above grade,
and two levels below grade. The historic Headhouse and
Tailhouse, which run parallel to one another, are connected
by seven wings.
The South Building has had
a long lifetime serving the needs of the thousands of
government employees who have used the facility to further
the nation's agricultural needs and perpetuate the stewardship
of the country's forests and rangelands. In the 1990s,
however, USDA personnel realized the apparent need to
renovate the building with new systems and also keep
the building up to code with ADA accessibility and life
safety requirements.
Plan Development
As it is responsible for all
government buildings' space leasing arrangements, the
General Services Administration (GSA) has established
tenant standards. One of the goals of the USDA was to
bring the South Building up to speed in this area. Brad
Crown, principal architect for the renovation who works
for Washington, DC based Shalom Baranes Associates explains,"They
[GSA] want their buildings to meet these goals and to
bring all up to current code as much as possible."
Due to the sheer size of the
renovation project, exploratory studies were developed
to see how construction should be carried out and what
could be done to preserve different aspects of the building.
Crown states, "we went
into the building cold; none of us worked on it prior
to our involvement with this. It [gave us] a chance
to develop what the building's status [was] on a range
of issues from life safety to ADA accessibility. We
took those parameters and came up with three options
to address deficiencies."
The project team which is made
up of a joint venture between Shalom Baranes, a project
management team from USDA, and the Washington, DC office
of Syska Hennessy devised a master plan for the phased
renovation of the entire building. The project would
include the replacement and upgrade of mechanical, electrical,
plumbing, life safety, telecommunications, security,
and vertical transportation infrastructure.
Initially, the master plan
broke the renovation into eight to 10 construction phases.
Funding and tenant relocation constraints could extend
that out to as many as 13 phases. To date, the team
has completed phases one and two and is presently engaged
in the renovation of the third phase.
Historical Preservation
Located just half a block from
the National Mall, the South Building is similar to
the style of many of the early 20th century federal
government facilities with its trademark limestone,
classic brick, and terra cotta elements.
There has been a movement to
make the South Building a landmark. Thus, a paramount
directive for the project was to keep certain areas
of the building intact, because they were considered
historic.
Michael Sazonov, project manager,
USDA explains, "We had to meet all the National
Capitol Planning Commission (NCPC) requirements through
[GSA's] Historic Preservation offices."
According to Crown, the GSA
was a go between for the project team and the various
local agencies that weighed in about their preservation
demands.
Sam Brunetto, vice president,
Syska Hennessy says that along with the entire Headhouse
and the Tailhouse, the other historically significant
areas include the first floor, basement, sub-basement,
and the seven wings that connect to the Headhouse and
Tailhouse.
Brunetto and his organization
has played a decisive role in maintaining the historical
integrity of the interior. "In those [historic]
areas, we retained the original corridor," says
Brunetto. "This work included renovating doors,
restoring windows, and installing a replication of the
original lighting fixtures."
Demolition And Build-Up
In its original incarnation,
the South Building housed seven miles of corridor. So
in stripping down the corridors and various areas, the
team had to be cognizant not only of the historical
aspects, but also had to make sure parts of the building
wouldn't come down.
"It's not difficult; it
just keeps you on your toes to make sure that any penetrations
through the floor respect the fact you want to keep
[the foundation in place]. You don't want to go cutting
up the wood jousts in your house, because that's what's
keeping your floor up," Crown says.
"In this current phase,
the middle third of the Headhouse is being renovated.
As the major east/west circulation path between all
of the building's wings, all of the floors' central
corridors are to be retained," Crown states.
In the areas which were not
deemed historic, USDA employees had a choice in how
they wanted to develop their office footprints. "Some
have opted for open office space and some of themabout
halfhave opted for fixed center corridors,"
Crown states. The fixed center corridors are close in
style to what was there originally.
HVAC
In accordance with the arrangement
the project team made with the historical preservation
organizations, the basements and the first floor could
not be changed. However, in the wings, floors two through
six could be altered by USDA.
The existing HVAC system consisted
of perimeter induction units on each floor and central
outside air handling units in the attic above the wings.
They were removed and replaced with central air handling
units located in the attic mechanical space above the
wings.
Brunetto explains that by using
vertical HVAC duct routing arrangements complemented
by smaller horizontal distribution ductwork, it helped
in preserving the lower floors' historic fabric. And
yet, it still gave the USDA the flexibility it needed
for space planning in the upper floors.
"We created bulk heads
on the office side of the corridor and used that as
a distribution raceway for air conditioning ductwork
to supply air to ceiling mounted variable air volume
terminal units," says Brunetto. "By putting
the air handling units in the attic and having vertical
duct distribution, we were able to work out a scheme
that allowed the duct distribution on each floor to
remain the same, yet gave the USDA the ability to alter
the layout of the floors as needed."
The distribution comes from
the attic; however, each floor has variable air volume
(VAV) terminal boxes. Each wing is equipped with approximately
28 terminal VAV boxes, giving employees greater freedom
with temperature choice.
Antiquated
Life safety features were a
significant part of the project, because the old fire
alarms would create massive problems for the smallest
incidents.
"There are about 6,000
people involved [in the building], and every time someone
burnt a bagel in the toaster, the fire alarm evacuated
the building. You filled up Independence Avenue,"
says Crown.
To combat this outdated evacuation
method, the building will have a selective evacuation
plan that is set up in three zones: east, middle, and
west. A voice activated fire alarm will evacuate the
floor where the actual fire is, and the floors directly
above and below it will be evacuated as well. Brunetto
says this is in accordance with high rise building codes.
Horizontal fire safety doors
are being installed, so people can evacuate through
the fire door out of the danger zone. The existing sprinkler
system protected only the basement, sub-basement, and
selected areas of the first floor. However, the entire
structure will eventually be protected with a combined
automatic standpipe sprinkler system.
Electrical Update
The electrical system was several
decades old and desperately needed to be updated. "One
of the big things we did in terms of electrical distribution,
[was to] convert the supply voltage," asserts Brunetto.
"The building is systematically being converted
from a 208/120 to a 408/277 volt secondary distribution
system. Through extensive pre-design survey and load
analysis, a methodology for upgrading the 15 KV distribution
system was established to demolish and replace the existing
transformers and secondary substation switchgear."
By making this change, the team was able to install
energy efficient lighting fixtures throughout the building.
Occupancy sensors were also
implemented, so that lighting controls would illuminate
rooms only when personnel were present. With the modern
equipment and efficiency
measures, energy costs are predicted to be reduced by
20% to 25%. In addition to updating the voltage in the
building, Cat 5 wiring and fiber optic cable were incorporated
into the renovation design, so employees will have the
most modern IT connections.
A main distribution frame room
has been incorporated in the attic of wing five. It
allows voice services to branch out to all wings and
be distributed to each of the telecommunications closets.
Renovating While Functioning
Several thousand employees
inhabit the South Building, and it was deemed essential
for the renovation team to undertake the construction
while most of the USDA employees continued to work at
the facility. In doing this, systems had to remain functional.
"They initially moved
about one wing's worth of people off site, so now it's
a scenario like musical chairs. Each time construction
stops, everyone has to change seats so they can vacate
the next space," states Crown.
The off site location where
the USDA relocated its personnel was the George Washington
Carver Center campus located in Beltsville, MD.
Moving Forward
When the renovation is complete,
it will allow the facility to house up to 6,800 USDA
employees. As two phases have finished construction,
many of the goals of the project team have been met,
but still there are more to achieve.
The team wants to qualify for
LEED certification. As the project is in its third stage,
sustainable principles are given greater consideration.
Back in 1997, during the team's
initial involvement, sustainability had just begun to
emerge as a design objective. However, there wasn't
any industry consensus as to what constituted a green
building.
Nonetheless, the project team
was able to identify a number of integrated design criteria
that would serve the USDA by reducing operations and
maintenance costs while helping to conserve energy.
Brunetto discusses that while LEED certification was
not in mind before phases one and two were cvompleted,
in phase three an effort was put forth to obtain certification.
"We decided that we would try to do as much as
we could in phase three under the guidelines of the
USGBC. The ultimate goal is to have the entire building
certified as it is completed."
The USDA has applied for credits
for innovation in attempting to reduce water usage in
phases one and two.
"Back before we even began
phase one, they [USDA] recognized they were using domestic
[drinking] water for part of the cooling system. They
converted that themselves," says Brunetto.
While challenged with an enormous
renovation, preservation measures, and a partial personnel
occupancy, the project team has continued forth in the
implementation of energy efficient measures and new
engineering systems.
The team's flexibility and
tenacity in working on such a grand project has kept
things moving forward and allowed the building to adopt
new measures. When the renovation is complete, not only
will the future of the USDA's South Building be assured,
but its history will remain intact.
|