|
Home
> Articles
By Issue > Showcase
> October 2004
SHOWCASE:
What's
Old Is New
Chicago's
Midway Airport has made a comeback and returned to its
glorious past.
By Heidi Schwartz
During its heyday
back in the 1940s and 1950s, Midway airport was at the
center of aviation. It even won the distinction of being
considered the world's busiest airport in the years
from 1932-1955. In that era, many Chicagoans were proud
of having a first class airport within its city limits.
Midway airport's
present location opened in 1947 with a standalone terminal
to meet travelers' needs. Forty years later, it desperately
needed a facelift.
By 1991, the
once grand airport was falling behind its much larger,
younger sibling'O'Hare International. By contrast, Midway
was down to a small number of daily flights, and in
November of that year, Midway Airlines (the local carrier)
shut down operations. Calls for the airport to be closed
were heard around the city.
While the airport
was neglected and seemed destined for closure, it did
have a savior. The city of Chicago committed to the
airport's resuscitation. Much needed help also came
from two discount airlines (Southwest and ATA) that
stepped up to lend their support by agreeing to fly
out of Midway; and a funding solution was reached by
the airlines, city and federal governments.
Project Directives
And Challenges
In the fall
of 1995, design for the expansion/renovation began.
Two architectural firms, Kansas City, MO-based HNTB
and Chicago, IL-based A. Epstein and Sons International
Inc. worked together on the project. The former was
the principal design firm and the latter was the lead
architect.
Tim Cahill,
vice president and director of design at HNTB explains
the city's desire to meet a certain business model and
praises city officials for sticking with their plans
for the airport.
'The city had
specific ideas what the building should cost; what they
could spend on it; how it was going to work'.From the
very beginning, it was meant to be an airport that was
nice but had to work for the [financial] numbers, its
location, and the airlines that serve that airport,'
says Cahill. 'If you build a fancy airport and it doesn't
make any dollars or doesn't work for the airlines there,
it's not very pertinent. [Midway] is one that works
well with the business model for the city.'
Additionally,
the project principals had to keep the airport operational
while construction took place, so the team was required
to keep a certain number of gates open throughout the
expansion. The existing runways could not be moved either,
due to spacing limitations. (Midway is located in the
middle of a residential neighborhood on the South Side
of Chicago.)
Cicero Avenue
And Parking Garage
Without the
ability to change the runway footprint, the project
team had to start construction on the road (Cicero Avenue)
that runs parallel to the airport in order to create
open space for the new terminal.
"The first
thing we did was have seven lanes of Cicero Ave. moved
further to the east," says Cahill.
Cicero Avenue
is a major highway that runs in a north/south direction
through the city. Due to its importance as a traffic
artery, the Department of Transportation (DOT) would
not allow for the complete closure of the road. In order
to work around this, the team collaborated with the
DOT to develop a lane closure strategy for the highway.
Night work was one alternative the team used for this
portion of the construction.
Along with moving
a major highway back to accommodate the rest of the
construction, there were several other large job elements
demanded by the project. These elements included: the
demolition of old parking lots; the creation of a six
story parking garage; and the development of a flyover
entrance into the terminal that ran above Cicero Avenue
to improve access and ease local traffic into the airport.
All this occurred outside of the construction on the
actual terminal. As the project was done in phases,
the principals on the job had to coordinate different
elements and aspects of the job. Cahill estimates there
were over 250 design phase sketches and gives an example
of the multitasking that became commonplace for the
project. "As we built the road construction, we
put in a baggage tunnel between the terminal and the
east side of Cicero and the concourses and the gates
building on the west side of Cicero," says Cahill.
Coordinating
numerous ongoing jobs while competing with the physical
layout of the airport complicated construction to some
degree. The terminal is located on the east side of
Cicero Avenue and is bordered by the runways. The old
airport's parking lots were on the west side of Cicero
Avenue. This major thoroughfare dissected the construction
site in half.
Allen L. Pomerance,
executive vice president of A. Epstein and Sons International
Inc. and project director for the Midway Airport expansion
explains the core of what the terminal aspect of the
project entailed. "We were designing a new airport
to be built on the site of an existing airport. The
phasing [of construction] allowed for sections of the
old building to stay open while the new building was
being built. Then, systematic demolition of the old
building took place. As the new building grew, the old
building shrunk."
HVAC Implementation
The airport's
original HVAC systems helped the team during construction.
"The old building was heated and cooled with rooftop
type units, so it was relatively easy to isolate a portion
of the building," explains Pomerance. The new HVAC
systems are housed in their own physical plant facility
on site.
The facility
management team played a significant role in the implementation
of the new HVAC systems by working with the project
principals on the phased commissioning process and subsequent
opening of the airport.
"The role
we played when we came on board was to work with the
Department of Aviation and its project management team
to help them understand the function of the systems
that went in and also get those things commissioned,"
states Steve O'Mara, general manager of Chicago, IL-based
Facility Service Professionals.
Taking On
Growth
In 1998, the
airport served 11.4 million passengers. This year, the
latest projections for Midway show the airport is expected
to serve 21.5 million people. O'Mara acknowledges the
demands of such growth.
'The biggest
challenge we face is keeping up with the relative success
of Midway. We are already nearly 20% in excess of the
estimated passenger flow at the time the building was
designed. We have to be ready to change what we do on
a daily basis'in most cases based upon a particular
load and particular areas of the building. It is a very
dynamic clientele, as you might expect in an airport.
It's not like an office building where people are sitting
in their offices all day. We get folks who come in here
for two to three hours, and depending on the airline
and the airline's schedule, we get those loads in specific
areas of the building. We have to manipulate our staffing
structures and workloads to address that dynamic clientele.'
O'Mara says
that the public areas such as the food courts and washrooms
are the high traffic areas that need the most attention.
Times Change
And So Do Airports
Ironically,
as Midway has made a comeback from possible closure,
O'Hare is now struggling with its own infrastructure
problems. Because O'Hare has been extremely busy this
year, it has exceeded its capacity levels and has experienced
numerous delays. However, the airlines and city officials
have been attempting to address this issue by restructuring
flight patterns and planning major renovations at the
airport.
While Midway
has surpassed its traveler expectations, it has maintained
its small airport feel and something travelers relish
most: convenience. When flying today, people expect
to have delays and downtime at their airport, and then
spend more time getting to a city's business district
even after they arrive at their destination.
"The biggest
thing about Midway is the convenience level....You can
fly right into Midway and get on the orange line [subway]
and go right downtown," states Cahill.
Once the epicenter
for aviation, Midway's rebirth has created a modern
airport able to accommodate greater traveler capacity
and at the same time help city officials market Chicago's
accessibility.
This article
was compiled from interviews with O'Mara, Cahill, and
Pomerance.
Do you work
in a setting that might have unusual challenges? Please
send an e-mail to schwartz@groupc.com.
Project Information:
Project: Midway
Airport. Type of Facility: New. Function of Facility:
Transportation. Owner: City of Chicago. Manager: Steve
O'Mara. Footage: 950,000. Budget: $750 million. Architectural
Firms: A.Epstein and Sons International (Lead); HNTB
(Design). Contractors: Clark McHugh Raugh. Construction
Managers: Kenny-Rust-Midway. Civil Engineer: McDonough
Associates, Inc.
Product Information:
Roofing: John
Mansville. Seating: KI-Kruger. Doors: Security Medical
Products.
|